FORGE / STRUCTURAL STEEL FABRICATION
01 / TONS FABRICATED
0T

Last 12 months

02 / AVG. DAYS TO DELIVERY
0

Approval drawings to truck

03 / CERTIFIED WELDERS
0

AWS D1.1 / D1.5 qualified

04 / PROJECTS DELIVERED
0

Zero RFI rejections

ASTM A992 WIDE FLANGE · HSS · PLATE — DETAILED, FABRICATED, AND DELIVERED ERECTION-READY.

AWS D1.1 · AISC 360 · OSHA 1926 SUBPART R COMPLIANT

Download Capability Statement
DWG-001 · REV-C · 2026-02-26
FORGE STEEL INC. · SHEET 1 OF 1
ASTM A992 Wide FlangeHSS Rectangular & RoundA36 Structural PlateCNC Plasma CuttingRobotic MIG WeldingShot Blast & PrimeErection-Ready DeliveryAWS D1.1 CertifiedAISC Member FabricatorOSHA 1926 CompliantComplex Moment ConnectionsShop Drawing DetailingASTM A992 Wide FlangeHSS Rectangular & RoundA36 Structural PlateCNC Plasma CuttingRobotic MIG WeldingShot Blast & PrimeErection-Ready DeliveryAWS D1.1 CertifiedAISC Member FabricatorOSHA 1926 CompliantComplex Moment ConnectionsShop Drawing Detailing
CASE STUDY 01
MEZZANINE PLATFORM

Resolving a Complex
Moment Connection

DENVER, CO · 2025
220 TONS · 6-WEEK SCHEDULE
Structural engineering blueprints spread on a drafting table with red markup clouds showing connection detail revisions
DETAILING PHASE

Redline clouds on moment connection at grid B-3. Beam-to-column flange weld detail resolved in 48 hours without RFI.

Close-up of engineering connection detail drawing showing bolt pattern and weld symbol annotations
CONNECTION DETAIL W-14×120

Full-pen groove weld + 8-bolt slip-critical connection. Fabricated to AISC Design Guide 24 tolerance.

CNC plasma table cutting steel plate with sparks flying in a dark fabrication shop
PLASMA CUT
0:42 HRS
Steel fitter positioning structural members on a layout table with clamps
FIT-UP
1:15 HRS
Welder in protective gear laying a fillet weld on a steel beam connection plate
WELD
2:30 HRS
Steel mezzanine frame standing completed in a fabrication shop before painting
PRIME
0:55 HRS
Completed steel mezzanine platform installed in an industrial warehouse, columns plumb and beams level with workers on the structure
FIELD PHOTO · DAY 42

Steel standing. Plumb. True. On schedule.

GC FIELD SUPERINTENDENT
"Forge read the connection details and caught a tolerance stack we missed. The iron went up clean — no field modifications, no delays."

Marcus Delgado

HARTWELL CONSTRUCTION · DENVER, CO

READY TO FABRICATE YOUR PROJECT?

Upload your drawings and we'll have a quote back in 24 hours.

CASE STUDY 02
6-STORY COMMERCIAL FRAME

1,400 Tons. 9 Weeks.
Zero Field Corrections.

SALT LAKE CITY, UT · 2024
1,400 TONS · W-SHAPES + HSS BRACING
Multi-story commercial steel frame under construction with crane lifting a beam section against a blue sky
ERECTION DAY 14 · 6-STORY COMMERCIAL FRAME
Steel column base plates being welded in a fabrication shop with sparks and bright welding arc visible
COLUMN FABRICATION
Structural steel beams laid out on a shop floor with piece-mark tags attached to each member
PIECE-MARK SHIPPING
Two ironworkers connecting a steel beam to a column with spud wrenches on a construction site
FIELD BOLTING
Completed multi-story commercial steel frame from ground level looking up showing all floors complete
FRAME COMPLETE
STRUCTURAL MEMBERS
2,840PCS
WELD WIRE CONSUMED
3.2TONS
SHOP DRAWINGS
486SHEETS
ERECTION SCHEDULE
63DAYS
STRUCTURAL ENGINEER OF RECORD
"We sent Forge a 300-sheet drawing package on a Friday. By Monday they had issued shop drawings for the first delivery. That's the pace we needed."

Dr. Priya Nair, P.E., S.E.

MERIDIAN STRUCTURAL ENGINEERS · SALT LAKE CITY, UT

DETAILING TOLERANCEAISC C-7.4 · ±1/16"
WELD INSPECTIONMT + UT · 100% CRITICAL JOINTS
PAINT SYSTEMSSPC-SP10 · 3-COAT EPOXY
DELIVERY METHODJIT SEQUENCED · NO STAGING YARD

WORKING ON A MULTI-STORY PROJECT?

CASE STUDY 03
HEAVY INDUSTRIAL CONVEYOR TRUSS

300-Ft Conveyor Truss.
Installed in a 72-Hour Shutdown.

PUEBLO, CO · 2025
480 TONS · ASTM A572 GR.50
Massive industrial conveyor truss structure spanning 300 feet across a mining facility with crane rigging visible
FIELD PHOTO · SHUTDOWN HOUR 68

300-ft span. All connections torqued. Conveyor running by Hour 72.

Large truss chord members being plasma cut on a CNC table with precise dimensional tolerances for heavy industrial application
CHORD MEMBERS

W24×162 top & bottom chords. CNC plasma cut to ±1/32" tolerance.

Welder performing full penetration groove weld on heavy truss gusset plate connection with back-gouging visible
GUSSET CONNECTIONS

Full-pen groove welds. UT inspected. Zero rejections on 48 critical joints.

Steel truss sections staged on flatbed trucks in sequence for just-in-time delivery to meet tight shutdown installation schedule
JIT DELIVERY

12 loads sequenced for crane picks. Zero yard staging required.

PLANT MANAGER · OPERATIONS
"We had a 72-hour window before the next production shift. Forge delivered every section in pick sequence. The crane never waited. The conveyor ran on time."
BW

Brad Weston

COLORADO AGGREGATE INDUSTRIES · PUEBLO, CO

PROJECT COMPLEXITY FACTORS

Corrosive environment — hot-dip galvanized finish

MSHA compliance — load-rated access platforms

Seismic Zone D — SCBF lateral system

Live plant — zero disruption to adjacent operations

TIGHT SHUTDOWN WINDOW?

We sequence deliveries to your crane picks. No staging yard needed.

SHOP CAPABILITIES

The Full Stack.
Nothing Farmed Out.

Detailing through delivery — every operation under one roof. When your drawings arrive, we don't subcontract the detail work or the paint. We do it.

STRUCTURAL SHAPES

W, S, HP, WT, C, MC, L, HSS, PIPE

PLATE WORK

A36 / A572 / A514 · UP TO 4" THICK

WELDING PROCESSES

SMAW · GMAW · FCAW · SAW · GTAW

NDE METHODS

VT · MT · PT · UT · RT

SURFACE PREP

SSPC-SP6 / SP10 · SHOT BLAST

COATINGS

EPOXY · URETHANE · HOT-DIP GALVANIZE

SHOP CAPACITY

42,000 SF · 30-TON BRIDGE CRANES

DETAILING

TEKLA · AUTOCAD · SDS/2

Your drawings. Our shop.
On your schedule.

Upload your structural PDFs and we'll return a firm quote with a delivery date in 24 hours. No ballpark numbers. No "we'll get back to you."

Download Capability Statement
FORGE STRUCTURAL STEEL INC. · AISC CERTIFIED · AWS D1.1 · D1.5 · OSHA 1926 SUBPART R
AISCAWSSSPCAISC 360